Art and Engineering

Concrete Quantity and Cost Estimator

Concrete volume for slabs, footings and columns with waste, bag counts, ready-mix order quantity and cost.

Elements (1)

Combine slabs, footings and columns in one takeoff

1.2 m³
m
m
mm

Waste & ordering

%

5–10% typical

m³

Supplier's minimum step

USD/m³

Your supplier's quoted price

Bagged concrete

Bag counts use the YIELD (volume) per bag — check the bag label

L
USD
L
USD
L
USD
L
USD
L
USD

Concrete volume

Net volume
1.2m³
1.57 yd³ · 42.38 ft³
Incl. 10% waste
1.32m³
1.726 yd³ · 46.62 ft³
Ready-mix order quantity
1.5m³
= 1.962 yd³
Rectangular slab ×1
1.2m³
Waste allowance
0.12m³
Ready-mix cost (order qty × price)
enter price

Bag quantities

60 lb bag — yield 12.7 L
104 bags
80 lb bag — yield 17 L
78 bags
Estimate only
Prices are user-entered. Approximate fresh weight ≈ 3,168 kg (typical 2400 kg/m³; shown separately — volumes are never derived from mass).
Assumptions & limitations
  • Prismatic element geometry exactly as entered.
  • Waste applied to net volume; ready-mix rounded up to the order increment.
  • Bag counts are rounded up to whole bags using the stated yield.
Limitations
  • No allowance for uneven sub-grade, formwork deflection, or reinforcement volume.
  • Confirm quantities with your supplier before ordering.